Posted on: July 22, 2019

Peachwood Park Upgrades Start in July

PEACHWOOD PARK 01_cvMain

Landscape improvements, a shade structure and new park equipment are planned as part of renovation at Peachwood Park scheduled to begin in July.

Crews from Senitica Construction will survey the park on July 23, with demolition scheduled for July 24. After grading and drainage improvement, crews will begin rebuilding the park in early August. A new shade structure is the first project, followed by concrete work, park furniture, irrigation and landscaping.

The work is scheduled for completion at the end of August. The park is at 21132 Peachwood.